Partnering Workshop
7 May 2026
EmployerCEDD
Project ManagerAECOM
Contract No. ND/2024/05

Kwu Tung North New Development Area, Remaining Phase

Improvement Works of Fanling Highway (Pak Shek Au Portion) and Associated Works
Contractor — Joint Venture Lanon · Sinohydro · Excel Joint Venture
Fanling Highway · Pak Shek Au Portion
01 / 25
Partnering Workshop
7 May 2026

Agenda of Presentation

01Brief Introduction of the Project
02Handover Area
03Progress
04Project Challenges
05Contractor Design
06Innovation
Agenda
02 / 25 JV
Section 01
Introduction
Section 01

Brief Introduction of Project

Brief Introduction
03 / 25 JV
Section 01 · Introduction
Contract Information
Brief Introduction

Contract Information

Contract No. and Title ND/2024/05
Kwu Tung North New Development Area, Remaining Phase: Improvement Works of Fanling Highway (Pak Shek Au Portion) and Associated Works
EmployerCEDD
Project ManagerAECOM
Contractor's NameLanon – Sinohydro – Excel Joint Venture
Starting date19 January 2026
Anticipated Completion Date5 December 2030
Tendered total of the Prices [Total Contract Value excl. Contingency]1,216M
Estimated forecast total of the Prices [Total Contract Value]1,818M
Brief Introduction · Contract Info
04 / 25 JV
Section 01 · Introduction
Scope of Works
Brief Introduction

Scope of Works

Site location map
Site clearance and formation (including land decontamination works);
Construction of associated works including water mains, drainage, retention tanks, sewerage works, roadworks, cycle tracks, footpaths, junction improvement, box culverts, slope works, retaining walls, street furniture, landscaping works, electrical and mechanical works and other ancillary works; and
Widening of Fanling Highway (Chau Tau to Pak Shek Au Portion);
Implementation of environmental mitigation measures (including noise barriers and low-noise road surfacing) and environmental monitoring works for the works mentioned above.
Modification of Castle Peak Road (Chau Tau Portion);
Construction of Pak Shek Au Interchange;
Modification of Pak Shek Au Bridge across Fanling Highway;
Construction of footbridge across Fanling Highway (Pak Shek Au Portion);
Extension of existing subways Nos. NS161 and NS161A;
Brief Introduction · Scope of Works
05 / 25 JV
Section 01 · Introduction
Completion Plan
Brief Introduction

Plan for Completion of each Section

Section map — Portion full plan
SectionDescriptionCompletion date
1Portion I, II, III, III-A, XII, XIII, XIV, XVI-A, XVII and XVII-A excl. landscape softworks & works in Sec. 1ATenderer's "Time" clause date — 1481 days after start (8 Feb 2030)
1ARetention tank & associated building (Drg. 6062908B/C3/1303, 1305) within Portion III-A and XVII-A, excl. landscape softworks1538 days after start (6 Apr 2030)
2Portion IV and VII, excl. landscape softworks442 days after start (6 Apr 2027)
3Portion VIII, excl. landscape softworks1781 days after start (5 Dec 2030)
4Portion V, VI and IX, excl. landscape softworksTenderer's "Time" clause date — 1481 days after start (8 Feb 2030)
5Portion X and XI, excl. landscape softworks518 days after start (21 Jun 2027)
6Portion XIV and XV, excl. landscape softworks990 days after start (5 Oct 2026)
7Preservation & protection of Existing Trees per Gen. Spec. & Particular Spec. Sec. 261781 days after start (5 Dec 2030)
8All landscape softworks in Portion I, II, III, III-A, IV, V, VI, VII, VIII, IX, X, XI, XII, XIII, XIV, XV, XVI, XVI-A, XVII and XVII-A of the Site1781 days after start (5 Dec 2030)
9Establishment works for landscape softworks in Section 8365 days after Sec. 8 completion (5 Dec 2031)
Brief Introduction · Completion Plan
06 / 25 JV
Section 01 · Introduction
Key Dates Plan
Brief Introduction

Key Dates Plan

Key dates site outline
Condition to be MetKey Date
Completion of the works of Civil Provision of TC55 in Portion I, II, III, III-A, XII, XIII, XVI, XVI-A, XVII and XVII-A of the Site necessary to facilitate ND/024/03 contractor to complete the T&C and SAT along FLHY KD11188 days after starting date (21 Apr 2029)
Completion of the works necessary for CLP laying cable along Portion V, VII, XIII and XVI of the site KD2488 days after starting date (22 May 2027)

* The completion date for the whole of the works is the date of 1781 days after the starting date (5 Dec 2030)

Brief Introduction · Key Dates Plan
07 / 25 JV
Section 02
Handover Area
Section 02

Handover Area

Handover Area
08 / 25 JV
Section 02 · Handover Area
Status ND/2024/05

Status of Handed Over Area on ND/2024/05

Handover area map
Handover Area
09 / 25 JV
Section 03
Progress
Section 03

Progress

Progress
10 / 25 JV
Section 03 · Progress
Subletting
Progress

Subletting

Supplementary Agreement on Amendment to NEC Clause 26 in ACC Clause I:1 and Clause VI:1 to VI:3

Packages
PackageDescriptionTo be AwardedAwarded SC SumSub-contractor
SC001Traffic Consultant30-Jan-26966,000.00Nolan Consultants Limited
SC002Temp Work Design18-Mar-26880,000.00JM & Associates Ltd
SC003Pre-construction Condition Survey of the Existing Structures11-Feb-26190,000.00Gallen Consultants Limited
SC004Initial Site Survey (Manual Survey)06-Mar-26252,000.00Golden Standard Survey Services Limited
SC005Tree Survey and Tree Risk Assessment06-Mar-26978,040.00Acacia Arborist and Consultant Limited
SC006UU Detection11-Feb-26244,129.50Hilton Detection & Safety Consultants Company Ltd
SC007CSD for Footbridge No 1 and Noise Barrier13-Mar-26990,000.00Mannings (Asia) Consultants Limited
SC008CSD for PSA Interchange bridges, PSA Bridge and Retention Tank06-Mar-26780,000.00AIS Infrastructure Solutions Limited
SC012DWSS (Digital Works Supervision System)06-Mar-26251,600.00Transcendence Company Limited
SC013Partnering Workshop17-Feb-2649,000.00JCP Consultancy Internal Limited
SC014Temporary water supply (3 inch pipe)06-Mar-26133,000.00Wui Chun Engineering (HK) Co Ltd
SC015Temporary power supply (400A)06-Mar-26113,000.00Wing Wo Water & Elect. Const. Co
Over $1M
PackageDescriptionTo be AwardedAwarded SC SumSub-contractor
SC017Emergency Unit06-Mar-26852,000.00Hang Cheong Engineering Limited
SC020Site preparation works06-Mar-26747,290.00Hang Cheong Engineering Limited
SC021Ground Investigation Works and Instrument Installation09-Apr-265,999,910.00DrilTech Ground Engineering Ltd.
SC024Asbestos Survey25-Mar-26270,000.00Met Green Consulting (HK) Limited
SC027Initial Site Survey (Mobile Mapping System) MMS06-Mar-26850,000.00The Earth Solution Limited
SC031Provision of Labour for Misc. Works06-Mar-26660,000.00Hang Cheong Engineering Limited
SC032Independent Safety Auditor12-Apr-26444,000.00Principal Consultant
SC010BIM modelling consultant14-Apr-261,325,064.00Vircon Limited
SC0094S (Smart Site Safety System)06-Mar-262,524,000.00Powerchina Zhongnan Engineering Corporation Limited
SC030CCTV inspection of existing drainage system16-Apr-26455,880.00Hilton Detection & Safety Consultants Company Ltd
Progress · Subletting
11 / 25 JV
Section 03 · Progress
Activities

Progress

Mobile Mapping
Mobile Mapping
Pre-construction condition survey
Pre-construction condition survey
Container office set up at WA2
Container office set up at WA2
Progress · Activities
12 / 25 JV
Section 03 · Progress
Upcoming
Progress

Upcoming Works in Half Years

Major Works
Site Clearance
Tree Survey
Implementation of TTA at Castle Peak Road
Ground Investigation Works
Piling Works
Demolition Works
Subway extension works
Progress · Upcoming Works
13 / 25 JV
Section 04
Project Challenges
Section 04

Project Challenges

Project Challenges
14 / 25 JV
Section 04 · Project Challenges
Summary
Project Challenges

Summary

No.Items
1Late Possession of Site
2Diversion of Underground Utilities
3Interface Contracts
4Congested Site Area for Retention Tank and Drainage Works near Fanling Highway
Project Challenges · Summary
15 / 25 JV
Section 04 · Project Challenges
Late Possession

If Late Possession of Site: Affect realignment of Castle Peak Road and overall Programme

Use the map to show the location of BU /HH that need to concern. Eg. Mr. Lam of HH4

BU/HH location map
Action Proactive PR visits
LocationUnitNameType16-Apr-26Remark
Luen Sang AreaBU1Mr. Ku飯堂YesNeed to meet his landlord
BU2Mr. Li車房YesNeed to meet his landlord
BU3車房
BU4光明士多
BU5花圃
HH1Mr. NgYesWaiting for financial settlement
HH2Mr. HoWaiting for financial settlement
HH3
Castle Peak RoadHH4Mr. LamYesNo rehousing arrangement by government
HH5
HH6Mr. ChungMaidNeed to re-visit on 25 April 2026
HH7
HH8
Project Challenges · Late Possession
16 / 25 JV
Section 04 · Project Challenges
UU Diversion

Diversion of Underground Utilities: CLP 132kV power cable, 11kV power cables, High Pressure and Medium Pressure Gasmain, etc.,

Action Early Planning of UU works
Underground utility diversion
Project Challenges · UU Diversion
17 / 25 JV
Section 04 · Project Challenges
UU Diversion
Project Challenges

Diversion of Underground Utilities: CLP 132kV power cable, 11kV power cables, High Pressure and Medium Pressure Gasmain, etc.,

UUChallengeFollow up
Existing CLP 132kV Cable at Castle Peak Road
  • Minimum of 18 months lead time for diversion
  • Outages available during winter only
  • Conflict with permanent structure
  • Early planning of the routing for 132kV diversion
  • Advance liaison with CLP for works order issuance
Existing High Pressure Gas Main at Castle Peak Road
  • 3-5 years lead time for diversion
  • Outages available during summer only
  • Conflict with permanent structure
  • Design review of the structure to avoid conflicts with existing gas main
Existing Hong Kong Telecom Cable along Pak Shek Au Bridge
  • Existing cables identified along PSA Bridge, which is to be demolished
  • Limited changeover joints available to avoid loss of signal
  • Long lead time for diversion and changeover
  • Design review on proposed Pak Shek Au Bridge to accommodate HKT ducting
  • Arrange coordination meetings for diversion arrangements to suit ND/2024/05 programme
Proposed CLP 132kV, 11kV and LV for Kwu Tung District Cooling System
  • Potential late land prossession to suit CLP commissioning schedule
  • Liaise with CLP for confirmation of the commissioning schedule
  • Liaise with Lands D/Interfacing Contract for handover schedule
Project Challenges · UU Diversion
18 / 25 JV
Section 04 · Project Challenges
Overlap

Overlapping working area with other Contracts, such as ND/2025/01

Action Close Interface Management
Overlapping working area
Project Challenges · Overlapping Area
19 / 25 JV
Section 04 · Project Challenges
Interface
Project Challenges

Interface Contract

Interface ContractKey IssueStatus
ND/2019/01 Handover at Pak Shek Au Interchange
  • Pre-handover Inspection on xx April 2026.
  • Tentative early handover for the slope near westbound of Fanling Highway
ND/2024/01
ND/2024/03 UU interface at Pak Sau Road Further liaison
ND/2025/01
  • Works arrangement at Castle Peak Road and omission of noise barrier
  • Extension of Footbridge No. 1 and DN1000 arrangement
YL/2020/02 Traffic Interface for Fanling Highway Agreed for the demarcation of handover areas
NMH Modification of retention tank and FB No. 1
Project Challenges · Interface Contract
20 / 25 JV
Section 04 · Project Challenges
Congested Site

Congested Site Area for Retention Tank and Drainage Works near Fanling Highway

Action Contractor Early Involvement in Design
Congested site area
Project Challenges · Congested Site
21 / 25 JV
Section 05
Contractor Design
Section 05

Contractor Design

Contractor Design
22 / 25 JV
Section 05 · Contractor Design
AIP Status
Section 05

Contractor Design

ItemAdvantageStatus
Alternative foundation of Noise Barrier
  • Less foundation dimension
  • Less traffic impact
AIP Report (Batch 1) Submitted
Alternative foundation of Bridge SR02, SR03, SR04 and PSA Bridge
  • Less pile numbers
  • Less construction time
AIP Report Submitted
Pak Shek Au Bridge
  • Less construction time
  • Less Traffic impact
AIP Report under preparation
Footbridge No.1
  • Changed into steel structures
  • Less site works
AIP Report under preparation
Retention Tank
  • Less excavation depth
  • Save ELS works
AIP Report under preparation
Contractor Design
23 / 25 JV
Section 06
Innovation
Section 06

Innovation

Innovation
24 / 25 JV
Section 06 · Innovation
06 items

Innovation

01UAV
UAV Safety Intelligent
UAV Safety Intelligent
02Bridge
Bridge Erection
Bridge Erection - Incremental Launching Method
03Digital Twin
Digital Twin
Digital Twin Data Fusion and Management Services
04DRA
DRA enhancement
Construction guidance and DRA enhancement services
05Safety
Safety enhancement
Collaborative Safety Enhancement Service for Personnel and Vehicles
06Knowledge
Project-Level Knowledge Base
Project-Level Knowledge Base Development
Innovation · 6 Tracks
25 / 25 JV